Development of verification program for safety evaluation of KNGR on-site & off-site Power System Design
  • Period
  • Aug. 2000 ~ Apr. 2001
  • Orderer
  • KINS

□ R&D goal

▪ Construction of the methodology to calculate load flow of power system inside and outside next-generation nuclear power plant
▪ Development of power system evaluation and verification program package and verification and analysis of domestic nuclear power plant
▪ Development and operation of the program for calculation and evaluation above

□ R&D description

▪ Grasping of nuclear plant power system analysis theory and algorithm
▪ Review of related condition and regulatory information and establishment of evaluation methodology
▪ Development of power system evaluation and verification analysis program package depending on analysis theory and condition
▪ Analysis and evaluation of next-generation and domestic nuclear plant power system through program package


                                                [Flow chart of transient stability]